The new 110 kV bay at RPZ Radogoszcz significantly improved reliability of electricity supply to consumers.
The cable and fiber-optic connection between two HV/MV stations formed a strategic node in the energy system.
The completed works increased the capacity for connection and transmission of electricity from renewable energy sources.
The project titled “Extension of the 110 kV Line Bay at RPZ Brzezińska in RPZ Radogoszcz” posed numerous challenges, including coordination and cooperation with the contractor for the 110 kV cable line in order to meet strict deadlines related to funding from the Cohesion Fund.