OUR CLIENTS’ STORIES

Station-battery replacement

CLIENT

PGE Dystrybucja S.A.

LOCATION

Pabianice, Sieradz, Sulejów, Radomsko, Łódź, Roszkowa Wola, Żyrardów, Brzeziny

YEAR

2024 - 2025

+9

new rectifiers

+1166

battery cells replaced
Challenge
The service life of many substation batteries was ending: capacity had become too low, rectifiers were damaged, DC wiring was obsolete and telecontrol links were absent. EU Regulation NC ER on system restoration also imposed new requirements. Most substations still had only a single battery section, so temporary batteries had to be installed during replacement. This involved additional risk because each station needs continuous DC supply to remain online for dispatch. The works had to be performed on substations in Retkinia, Janów, Sulejów, Lodowa, Pabianice, Roszkowa Wola, Komuna Paryska, Sieradz, Jawor, Żyrardów and Brzeziny.
Solution
At every listed site we replaced the battery sets with new, higher-capacity units, supplied matching racks and new cabling, and installed enlarged DC protection boards that allow a portable battery with rectifier to be plugged in. Missing LEM measurement transducers were added, defective rectifiers were replaced (or additional primary rectifiers installed) and a telecontrol link was configured so dispatchers have remote visibility of signals and measurements.

Summary

Replacing batteries, rectifiers and cabling increased substation reliability, functionality and autonomy in emergency conditions. Thanks to the professionalism of our team, the work was completed efficiently and on schedule.

CASE STUDIES

Our key projects

View all projects